Short answer
The governing rule is that production is not touched until cutover. First the upgrade is prepared; then the technical team creates a test copy with your real data already on the new version; you test it with your usual operations and approve it; and only then is the cutover scheduled.
Your company needs to decide quickly about modules and special developments, confirm the start, have your users test before the deadline, give your approval, and organize your team during the maximum downtime you are notified of. Without your approval, the cutover is not scheduled.
Length 72 min · in Spanish · process demonstration.
What you will see in the video
- 00:00 · Why an upgrade gets postponed
- 01:03 · Who this video is for
- 02:55 · The map: phase 0, phase 1, phase 2, cutover and closing
- 04:33 · Phase 0: prepare and open the upgrade task
- 22:09 · Phase 1: the technical team takes the task
- 28:20 · Phase 1: the test copy with real data
- 42:01 · Phase 2: the customer tests and approves
Why an upgrade gets postponed and what postponing costs
According to the author, an upgrade gets postponed month after month because it is scary, and the problem is almost never the technical side: it is the lack of order. Loose tasks, half-finished tests, an improvised cutover, and a customer who finds out too late what they are supposed to do.
Staying on an old version also has a cost: you miss improvements, you lose support, and every year that passes the jump gets bigger and more expensive. Also, if you fall out of the last two versions, you lose Ganemo's upgrade and support guarantee.
The stages of an upgrade, in order
There is one rule above all others: production is not touched until cutover. Everything is tested on a copy first, and the customer approves before anything moves. While it is being prepared and tested, your production database keeps running as usual and no user is affected.
| Stage | What happens |
|---|---|
| Phase 0 | The upgrade task is prepared and opened, and the modules the database has are reviewed. |
| Phase 1 | The technical team makes a test copy with real data, already on Odoo 19, and reviews it thoroughly. |
| Phase 2 | The customer approves the copy with their usual operations. |
| Cutover | The moment your Odoo actually moves to the target version is scheduled. |
| Closing | A few days of stability during which the previous version is kept intact in case you need to go back. |
Phase 0: prepare before launching anything
Each instance being planned generates its main upgrade task, which is used to follow the entire process, including customer follow-up. Before opening anything, the system warns about instances for which the upgrade cannot be done and explains why: it is not a production instance, it already has an upgrade in progress, or it does not have an active subscription.
In this phase the installed modules are reviewed one by one, looking for their equivalent in Odoo 19, and it is checked whether the upgrade is covered by the guarantee. If applications still need migrating, engineering tasks are created. A person reviews the checklist before continuing, and a message is sent to the customer to confirm the start.
The author insists that this is where most upgrades fail before they even start: the migration is launched without knowing what modules the database has, and the surprise arrives on cutover day.
What you, as the customer, have to do
- Before starting: reply quickly about which modules or special developments you have and which you no longer need, and confirm the start date they ask for. Every third-party module that is uninstalled is one less risk.
- During testing: pass the test copy link to all your users so they do their daily work in it, and tell the upgrade team if something is wrong, before the deadline.
- To close testing: write back to say the tests went well and they can proceed with the upgrade.
- At cutover: organize your team during the window in which Odoo cannot be used; ideally schedule it outside your operating hours.
A typical decision in phase 0 is to stop developing a module, or not to buy again an app from the Odoo store because Odoo already covers it natively.
The test copy: real data, production untouched
The technical team creates a copy of your production instance and brings it to the target version. The copy includes the attachments and is neutralized: it cannot send emails, issue invoices, sign tax documents electronically, or send them to the tax authorities.
The time depends on the size of the database: with 100 megabytes it can take minutes, and with hundreds of gigabytes, hours. In the meantime, it does not affect you at all.
Before it reaches you, the technical team tests the copy: that the main menus load and that there are no obvious errors. The status saying 'ready to test' only means the basics started. If there is an error, it is fixed and the copy is rebuilt with the corrected code, without repeating the whole upgrade cycle. The copy is automatically decommissioned on a set date, and testing must be done no later than that date.
Phase 2: you test and approve
When the technical team considers the copy good, you receive an email with the link to log in and test. Your production database is not touched and your users keep working as usual. The author asks each user to log in and do their day-to-day work: record an invoice, look at a report, reconcile a bank, review the website, set up a campaign or send a quote.
If something is not right, you let the upgrade team know, as the same email indicates. It is fixed, a new version of the copy is prepared, and you receive a new email so you can test again. This cycle repeats as many times as needed, and while it lasts the main task stays in phase 2.
Testing properly is your responsibility as the customer. When you are done, you reply with your approval. At that point the process moves to cutover and the test copy is marked as approved.
The cutover: date, maximum downtime and notices
Cutover is the date on which the old Odoo version stops being used and the new one begins. When scheduling it you choose the date, the time, and the stability days, which are the days the previous version is kept. If you pick a time when other processes run, the system warns you.
The expected maximum downtime is also shown. It is not made up: it is what the migration of your own test copy actually took, plus a few minutes of margin. In the video demo, the migration of the copy took 7 minutes, the migration budget was 40 minutes, and the expected maximum downtime was 2 hours and 27 minutes.
Before scheduling, two checks are done: the webhooks and the watchdog, an independent process that alerts an infrastructure channel if the cutover silently hangs. When scheduling, the customer receives an email with the date, the support channels and the expected maximum downtime. If the date needs to change, the customer is notified first; then the schedule is cancelled with a reason and rescheduled, and another email is sent.
The nine safeguards before cutover
When scheduling, the system checks nine things. If any of the first eight fails, the cutover does not start and nothing is touched; the ninth only warns.
- There is a test copy of the upgrade that has been tested and marked as approved.
- The cutover falls within its allowed time window, outside nightly maintenance, and does not overlap other jobs.
- The engineering task is closed: the customer approved.
- There is a recent, verified backup of the production database.
- The attachments are copied and verified.
- There is no other cutover in progress on the entire platform.
- If the customer uses the SQL connector, its connection is ready for the new version.
- The final instance was built with the same code as the approved copy.
- Warning only: no module was installed in production after the copy without code for version 19 or an implemented migration recipe.
If you rebuild the approved copy because you made a fix, the approved mark is removed automatically and must be set again. If you are a partner, the author recommends turning this list into a mandatory checklist before every cutover, even if you do not have a system that checks it.
The cutover in progress and rollback
During cutover your customer cannot log in to Odoo. The old production database is shut down for safety, the migration is launched, and everything is recorded in an immutable event log, which serves as an audit trail. If anything fails at some point, the system rolls back on its own and leaves the previous production running.
If cutover goes well, the customer logs in at the same URL as every day and is already on the new version. They receive an automatic email that says what is recommended today and where to get in touch if something fails.
What is kept and what happens after the upgrade
- The same URL and the same database name.
- The same user, the same password and the same two-factor authentication.
- External connections (Make, n8n, Power BI, Excel, or any service via SQL connector or API) keep working the same way, without configuring anything again.
- The new production database starts generating its backups automatically.
The previous version is kept as a backup for 28 days, or fewer at Ganemo's sole discretion, at its own URL. It is inactive by default and is activated by requesting it from the support channel, only in a critical emergency. After that period, the task closes on its own.
After the upgrade there is also a promotional support pack for the following seven days. It is not mandatory: you can learn from the public manuals.
Frequently asked questions
Do you want us to do your next upgrade with you?
Write to us at leads@ganemo.com.
00:00 An Odoo upgrade that is easier than ever. And no, it is not magic, it is having a process. If you have ever done an upgrade, you probably know this story. It gets postponed month after month because it is scary. When you finally do it, a module stops working, a report has changed, a user cannot invoice first thing on Monday when it is most urgent, and nobody knew who had to check what. The problem is almost never the technical side.
00:32 It is the lack of order: loose tasks, half-finished tests, an improvised cutover, and a customer who finds out too late what they are supposed to do. And staying on an old version has its cost. You lose improvements, you lose support, and every year that passes the jump is bigger and more expensive. That is why we are making this video so complete; it is going to be a bit long, and it is a video for you if you fit one of these three profiles.
01:04 It is aimed at three types of people. First, if you are a Ganemo worker, if you are part of our team that does upgrades or you want to be part of our team and be able to run an upgrade process without any scares. Yes, we want you to watch this, so that if at some point you start working at Ganemo, from day one you are already producing, and it will also help you so you do not apply to work at Ganemo if you do not agree with what we...
01:36 The second type of person is a partner or Odoo consultant who manages upgrade processes for their clients. This will help you take from the process what is useful, so that your upgrade projects are not chaotic. And finally, the third type of person who should watch this video is you, the client, who wants to understand what happens to your Odoo during the upgrade and what your role is so that it goes well.
02:07 It is also a video for you. We are going to show you a real upgrade from Odoo 18 to Odoo 19, from start to finish. How are tasks planned? How is a test copy prepared and validated before touching your production database? When does the customer come in to validate and do their tests? How is the cutover scheduled at a safe time, and what is checked afterwards to close everything with confidence? If you follow the process to the end, your next upgrade is going to stop being a
02:42 Leap into the void. But first, subscribe to the channel, turn on the bell with all notifications, and tell us in the comments if you have ever had a painful upgrade process and what you learned from it. So before we enter the Odoo screen where I will show you everything step by step, I want to explain the map, because the whole video will follow this order. There is one rule that outranks all others: production is not touched until cutover. Everything is tested on a copy first, and the customer approves before we move anything.
03:16 You will see that we talk about phases. Phase 0: the upgrade task is prepared and opened, and you review which modules the database has. In phase 1 our team works: it makes a test copy with real data, already on Odoo 19, and reviews it thoroughly. In phase 2 the customer approves it with their usual operations. When the customer approves, we move to cutover. The moment when their Odoo actually moves to the target version is scheduled.
03:48 Then comes closing: a few days of stability during which the previous version is kept intact in case you need to go back, and when the upgrade ends, it closes on its own. And something important for the tN: when it finishes, it keeps the same web address, the URL, the same database name, and if it has external services connected, like Make, n8n, Power BI, as well as Excel or any other service via SQL connector or via API.
04:20 Everything keeps its same connection and you do not have to configure anything new; everything keeps working. If you are a customer, keep this one key moment in mind: phase 2 is the testing, your Odoo 19 with your own processes, and without your approval nothing is scheduled for cutover. Here we start everything in our software-as-a-service application. As soon as we log in, we see a list of our databases, and each of these cards...
04:52 What we see here, in this case there is only one, but each card belongs to a customer with its version, its environment and its status. Right now you only see one because it is our example for today and I left a filter set, but whoever manages the upgrades, our functional upgrade team, our upgrade process managers, here there will be thousands of cards, and if you remove this filter, all of them will appear. Imagine this screen full of cards without the right training...
05:27 You would enter a state of anxiety, stressing out and thinking, wow, I have to plan the upgrade of thousands of instances that are different versions, clients, countries. How do I schedule it? How do I organize myself? As always, a lack of skills and competencies leads to stress. You reach the point of taking on the job calmly and you get overwhelmed. But if you are prepared, nothing happens.
05:58 You know how to face what has to be done, and that is the idea of this video: to give you that knowledge and those tools. From here you can easily choose which databases you want to prepare, plan them, and the same system will tell you which ones you can prepare and which you cannot, and why. The full explanation: if you are a partner, this is the first lesson for you: your upgrade list cannot live in a spreadsheet, in an Excel, or in your head.
06:31 It has to live where your instances are, so that for each one you know what step you are at. Let's start with this planning. We select the list of instances we are going to plan. You can use the search and filter options to decide which ones to filter. For example, all those in the same country, all those on a certain version, according to some tag. You build the order of pools or groups you want...
07:01 Plan. For now there is just one, but imagine if you select 50 instances, 200 instances. Click the Actions button, plan upgrade. A project appears, because yes, plan upgrade essentially creates tasks, which in this case will be assigned to the upgrade team, along with the target version and the instances. For this example there is one, there could be more. There is also a message about what Odoo is going to do, from the wizard, so you will see that in...
07:34 The other steps are similar. Odoo always helps us by warning us what it will do before we run anything. If I had selected the 50 instances I mentioned, or the 200, a new block would appear below indicating which instances the upgrade cannot be done for, always explaining the reason. Maybe an instance is not production; by mistake you selected one that is not production; maybe it is an instance that already has its...
08:04 Upgrade already in progress, and you did not filter it well, you selected it, or it does not have an active subscription. This way, nothing opens by mistake, nothing gets planned by mistake, and no task gets duplicated. Now that I understand what will happen when I press open phase 0, I click it, and we see that a task has been created that we are going to call the main Upgrade task. For what? For each instance. Each instance I selected will generate, or create, its main task.
08:36 And from here the whole process is tracked. Each phase will be a stage in the task. That is why you see here phase 0, phase 1, phase 2, cutover and closing of the upgrade. That is six stages if we count the final stage of done or finished. And this task is linked to the production database, that is, the customer's record, the instance.
09:06 And once this phase 0 starts, it implies there are tasks. The phases are very important controls, linked to real work, to activities that have to be carried out. But since we are in the age of artificial intelligence, much of the work is executed by our AI agents. In our organization, artificial intelligence is at the same level as the human; they are additional members of the team. Therefore, in this phase 0...
09:38 I am going to assign the activity to an artificial intelligence agent. I plan the activity, I will choose here 'upgrade phase 0', and I will look for my agent. Notice that I could have it assigned to me, or assign it to any other team member, or to an agent, which is still a member of the team. In this case, Dexter Soprano is an AI agent specialized in phase 0...
10:08 Of the upgrade, and we save the changes, assigning it to him. While Dexter takes the task and does his work. Here is a quick review: look at the description, it has a complete checklist we have to meet. For now no tasks block this task, but Dexter will check whether there is any task we must do before this moves to the next phase. And remember we have the 'Upgrade' tab linked...
10:39 To the customer's instance, and the source version and the target version. Dexter will not take more than a couple of minutes to do all his work, let's hope. And the process finished. What has it done? It entered the customer's database, read every installed module one by one, checking whether there is an equivalent in the new version 19. It gives us a report on everything related to its work, it identifies whether there are modules missing in...
11:11 Migrating, whether they are available or not. It checks whether the upgrade is covered by our guarantee, and it looks at what it says: covered by the guarantee means it is within the versions before the current one and it has an active subscription. Even if there were commercial matters to address, it has already scheduled an activity for our sales team so they can handle the customer's questions or commercial issues, for example if some applications are not covered by some maintenance fee...
11:42 Maintenance, and it had identified applications that needed migrating, it would have created the engineering task for the team that has to migrate those applications. In this case it did not create them, because at this point, for version 19, there are no applications to migrate. Everything is ready. But it can happen, especially when you start upgrades and a new version has just come out, that there is one or another application that does need migrating, which this customer simply...
12:13 Uses. And here it brings us the tasks automatically. A review and a level of work that used to take a person hours. Today Dexter leaves it ready in minutes, and with a much higher level of confidence. It makes fewer mistakes than a person. And what remains on our side, on your side, as the upgrade lead, as a member of the upgrade team, are the decisions. Of course, the decisions remain with us: human in the loop. But also the important responsibility.
12:49 If Dexter Soprano made a mistake, it is not Dexter Soprano's fault. Whose fault is it? Nobody's. It can make a mistake. But that someone makes a decision based on something wrong, that is your responsibility, it is your fault. If an error is identified and not fixed so that it does not happen again next time, that is also your responsibility. There is a culprit, which is basically the person responsible who is not meeting their responsibility. So, as a member of the upgrade team...
13:22 Upgrade, you are responsible for making sure Dexter not only does his work well but keeps improving. If you detected an error, something he did not quite do right, it is not that you go and fix it. No, the one who has to correct it is Dexter himself, making sure that next time he will not make the same error. Let's go back to the description. Each task has a very important verification, and we have to make sure all of it gets completed.
13:52 Why doesn't Dexter tick it? Because you, as a human, still have to check that everything Dexter did is right. Right, check the list of modules, for example: done; our own modules have their corresponding branch in 19: done. All of this is basically supervising Dexter as his supervisor, based on the messages he left you and the review he did, which, as you can see, is there in full. Based on all that, you say: he did it, complete, complete, and...
14:25 Well, the customer confirmed the start and opens it. Remember I told you this is the main task from which all the tracking happens. That includes tracking the customer. So you have to send a message to the customer confirming that the upgrade starts. And one might think, why notify the customer? Is it simply about the upgrade? No, because the upgrade often requires time from the customer. Not often: always. Coordination with the customer, so they test, familiarize themselves and get trained on the...
14:56 New version, and maybe at this moment they do not have time for it. We are approaching it at a bad moment for them, because maybe they have campaigns, because it is a busy time of the year, because they have to secure the accounting team and the accounting closes for whatever reason. It may not be a good moment for them to focus time and attention on an upgrade process. That is why there is a communication process with the customer, in which the customer says: fine, proceed, based on these estimated times. Yes, we...
15:28 With upgrades, we suggest that when customers receive our message that an upgrade has to happen, they make an effort to accept it, because remember we are racing against time because of the support deadlines and keeping the guarantee. If we stop being on the last two versions, you lose that upgrade and support guarantee. And once we complete this, we go to the tab...
15:59 Of upgrade, and here we mark 'checklist completed', and we have to make sure that checklist gets completed. I try to save the changes and it does not let me, because I told you we need to make sure the checklist is ready. I deliberately did not complete it so you can see there is an extra control measure. It makes sure you meet all those requirements. And only then do we activate this option. We save, and you see a...
16:31 New button: create the related task, which only appears once we are sure all those steps are complete. Why? Because this phase 0 is the preparation phase, and this is where most upgrades fail before they even start. Because the migration is launched without knowing what modules the database has, and the surprise is on upgrade day, on cutover day. That is why this checkbox cannot be ticked unless we have completed that list.
17:04 If you are a customer, your role here is simple but important. In the communications you have with our upgrade management team about which modules or special developments you have and which you no longer need, and the start confirmation date they will ask for, it is important that the communication flows, that you respond quickly and that decisions are made quickly. Sometimes a decision may be: this module I am no longer going to develop. This application I bought in the Odoo store, I am no longer going to buy...
17:36 For the new version, because Odoo covers it natively in a different way, and it is better to adapt to how native Odoo works. Whatever is required now in this process, we ask for quick answers and an ability to make decisions that do not slow the upgrade process down. Remember that every module that goes unused, every third-party module you decide to uninstall, is one less risk in the upgrade process.
18:06 Now, right after this preparation phase is completed, the functional upgrade manager clicks here: create related task. This new wizard opens, showing the title the task will take and the project it will be in. It is important to use the project the engineering team has access to. That is 'Upgrade Engineering'. The initial stage appears, and the assigned person.
18:37 This would have to be a human member of our upgrade team, because for now humans are still the ones responsible for this technical upgrade process. But for this example I will leave it to Dexter, don't bother me. Remember Dexter was our AI upgrade specialist. I will leave it to him, and we create the task. This task is created with its own technical lead. Remember: a human member of the upgrade technical team.
19:09 Which is in the backlog stage. And the main task, if we go back here, we see the main task is still in phase 0. But this related task we just created, for the upgrade technical team, arrives or starts in its backlog stage. Here is the idea that organizes the whole video, because there are two tasks and you have to understand that difference. The main task is the one facing the customer, and it moves through phases.
19:40 It is directly managed by someone responsible for the upgrade process, a functional lead. It is the upgrade manager, the functional analyst for that upgrade. They are the one in contact with the customer, and that main task moves through phases and guides the whole upgrade process, because it gives us a clear view per instance. Remember: one task or one instance gives us a clear view of which phase of the upgrade we are in.
20:11 On the other hand, the engineering task we created is like the steering wheel, because each time something important happens in this engineering task, the main task gets updated automatically; it moves on its own. We will see that in a moment with a real case. With the real case we are applying: why is it born in backlog? Now, pay attention, upgrade technical team: let's put on the hat of the engineering technical team...
20:45 Technical team: when we access our project manager, where do you go? Here, well, actually you go to see all your tasks, because you can see tasks from several projects. But now, so that not too many tasks open, I will enter this project where I already have a filter to see only one task. But here you will see your whole task pipeline in backlog. You could have hundreds of tasks, and some more in doing, and some others in testing. Here you have a complete view as...
21:19 Technical manager or as part of the technical team. That overall view lets you know what you are doing, what you have in backlog, which is the next one to take, how many you have in testing, and so you advance your work very quickly. Now, what does backlog mean? It is the engineering queue, what nobody has started yet. When an engineer takes it and moves it to doing, as you see, I am moving it to doing, which means I am about to start work.
21:50 On this task, who is starting the work? The engineering team. And what happens to the main task, which is the one the functional upgrade team sees? Let's go see it. We change hats, go back to the projects, and the upgrade team has its own project, where we see that its task is already in phase 1, automatically. A moment ago it was in phase 0, but since the engineering team already took...
22:23 The task and started it, it is already in the upgrade technical work, which is why our task is in phase 1. Understanding this, what I am explaining about the phases across the different projects, is key, because each person responsible will see many tasks in their pipeline, hundreds, even thousands, I would dare say. And if you do not understand what each thing means, you will feel lost in...
22:56 The middle. Once I understand it, I already know what these cards in phase 1 mean and what I have to do about them. The same goes for the tasks in phase 0: what I have to do regarding them. And so on for each phase. For example, phase 1: I do not have to do anything. It is there, and what it is telling me is that the engineering team is already working on it. So from my pipeline I have that overall view. We change hats again, to the engineering task. When this task moves...
23:28 To testing, what does it mean? It means the upgrade team has finished. In a moment I will explain what to do to get it to testing, but at the flow level, so you know where you are: if this moves to testing, I move it to testing, I will not do it now. What does it mean? It means I finished my upgrade process, the technical part, and the main task will automatically move to phase 2. And I go back to my project as the upgrade functional manager, and I will see this task in phase...
23:59 2. And I know what it means for it to be in phase 2. And if in the end everything moves automatically based on what happens in engineering, why create so many stages? Why not just have it in one stage and let engineering manage it? No, precisely because you are the upgrade manager for a reason: through this pipeline, with that overall view, you are the orchestrator above everything, and you find out where each thing is, what its situation is, its status, and you will know that...
24:32 All those that are in phase 2 are there because the customer already received the first communication to start testing their upgrade, testing on the new instance created for them. Now, what if the customer has an observation? During the whole testing process there is a lot of communication, and sometimes there are incidents, observations, customer questions. While it lasts, it stays here in phase 2. If because of some observation we have to send the engineering development task back...
25:05 To engineering, we have to move it back to doing. It does not matter, you move it back, but the main task stays in phase 2, so we know we are in that interaction with the customer. While that task is in phase 2, I will move for a moment: the engineering task may well move from doing to testing. If there is an observation, it goes back to doing. It can even have multiple tasks it depends on, which must be solved before going back to testing. But this engineering task has a cycle...
25:41 Of development, from doing to testing, and it will run that cycle as many times as needed until everything is resolved and the customer is clear and all their observations have been raised. And while that happens, the main task stays in phase 2. And when it is finished, when the tests in the testing stage pass, the customer confirms everything was a success. Finally, it moves to done, which also automatically moves the main task.
26:15 So if tomorrow someone asks how the upgrade of such a company is going, even I myself can ask how my upgrade is going, how this upgrade is going. The answer is here, in a complete task manager, not lost in a chat, on WhatsApp, in an email. Anyone who enters and has to pick up or take on some responsibility enters...
26:45 The Upgrade project and can see all the tasks, thousands of cards, and understands what each thing means. What is the pending work? And if they open a task, inside that same task, is all the detail of what has happened with the upgrade process. And for the engineering team it is key too, because what we are doing orders the day-to-day. We need our engineering team hyper-focused.
27:17 And you know that when you enter here, everything in backlog, what is not started but has been assigned as a task; everything in doing is what they are working on at that moment, probably no more than two or three tasks in doing at the same time, and that is what they have to resolve right now because it is in execution at that moment, because it is an observation that has to be raised. And what is in testing is there because it is no longer on their court as engineering. Everything that went...
27:47 To testing, I forget about it, it is already on someone else's court. But now comes when something has to pass to testing. I cannot pass just anything to testing so I can forget about it and say it is no longer on my court. No, no, no. There are unavoidable quality requirements to meet. Now that we have this overview of how task management works in both projects, because there were two tasks, you know each one in its own...
28:17 Project, and you have an idea of how they move between each other. Now let's focus on the engineering part. We put on the upgrade technical engineer's hat. Pay attention: if you want to work at Ganemo doing upgrade processes, on the technical side you will see your tasks. Where do we start? In backlog, and you take a task. What does taking a task mean? That I move it to doing, which is what I just did; the task is in doing. What was happening at this point?
28:47 Remember that the main task automatically changes to phase 1, so you do not have to be writing to the upgrade support team saying 'just in case, I already started this'. No, they find out automatically, because the tasks move in their pipeline automatically. And it is your duty, through this task you are taking, to make sure you leave ready and reviewed the upgraded instance of the...
29:17 Customer on the new version, by creating a test copy. In other words, you have to make that test copy, integrate it and leave it ready on version 19. But how do we do that? That is what I am going to show you. Remember that each task had here its upgrade tab. You can access it because it is directly linked to its instance, its record. Enter. Click the Upgrade button.
29:47 Choose test database. As we have seen, the wizards help you with what you have to do, or how it affects you once you confirm. Click create and launch, which opens the copy's record. This is a copy of your customer's production instance, but it is exactly the one that will be taken to the new version. At the top we see a banner that says what step we are at and how long it has been taking, and how long it will take. For example, it says...
30:23 Creating an instance, a database role, the image with the customer's modules, and it has been doing that for a minute; it takes about four minutes. And it says: when finished, the upgrade starts on its own. No need to do anything. We will notify you when it is done. In other words, from here on, all the work is happening in the background, and it is happening on its own. Not only has the record been created, the new database has been created, it...
30:54 Is migrating that database, and when it finishes I will have my database migrated to the new version. Is it really that easy? Yes, that easy. And we come back, because this will still take a few minutes. If I want to know more, I could tell it to update. Let's see whether anything has changed in the last two minutes, so we are not just sitting here waiting. I am going to go back to the main record of the customer's instance, and here you see the smart button...
31:27 Upgrade, and it already has an upgrade in progress, an upgrade instance created. So at any moment, if you want to enter that upgrade instance, you can also do it from the customer's main record. Let's go back to the main task. Sorry, it is not even the main task, it is the engineering task. As an engineer you started from your task, and here we go to the Upgrade tab, and you see that from your task you already have the test database created that you are working the upgrade on.
32:00 Everything from your task, to make your work easier, and directly from there we can also enter the instance. You do not have to link anything. Look, there is a new status here: it says 'creating the empty database where the upgrade will be restored'. It takes a few minutes, and as we keep clicking refresh we can check what happened. For example, here the upgrade is already in progress. And how long does it take? It depends on the size of the database.
32:31 From 100 megabytes it can take minutes, up to hundreds of gigabytes, which could take hours. That is why the key is here. It says: no need to do anything. What does 'no need to do anything' mean? That I stay with my arms crossed and do nothing? No. Be careful about taking this as a literal instruction about your duties. It means you can leave it there in the background, working. If I go back to my task pipeline, I want to go, for example, to all the tasks...
33:04 Of upgrade I am on. This one is in doing, it is being worked on. I know. But since I know it is progressing, I am going to take another task. Where do I take the other task from? From my backlog. There I must have many cards. And you will have many cards because you have a weekly upgrades target to meet. So you go to the next card, repeat the process, go to the next card and repeat the process, and you have to be working on several upgrades at the same time. It is not that I launch my upgrade and then, well, I am going to go play gTA [sic], which just...
33:39 Launch it, and I do not keep going to the next one, and the next one, we do not stop. The technical side is all produced by the system. It is important for customers to know that while all this is going on, it does not affect you at all in this process. Yes, a new test database was created next to production, but your production database keeps working as if nothing happened; they do not notice a...
34:09 No user is going to be affected, so on that front you can rest easy. What is running in the background is the copy of the database, the technical execution of the upgrade process, the restoration of everything, with its updated image on the target version. For this example, the target is version 19. The attachments are also copied, and it is going to be powered on, neutralized and validated.
34:40 That neutralization process is key. All of this that I am telling you happens on its own, though it is not automatic. We do not have to touch anything. Neutralizing, by the way, means that the copy being created cannot send emails, cannot invoice, cannot issue the electronic signature for tax documents, nor send them to the tax authorities; and your integrations are halted. If they have been well developed, they have to include a neutralization process that we run.
35:11 And you, as the engineering team, simply try to bring into doing all the tasks you can, and the ones you can already advance, you advance. For example, this one, since its instance has probably been ready for some time. Let's see: we enter the test database; the process should have finished. We enter the instance; it should already be done, and there it is. We see the result in green. And it tells us that the neutralized copy is ready at this link.
35:47 So we could already access our new Odoo, our database on the new version of Odoo. Then it warns us that this gets deleted automatically on the date indicated in the upgrade tab. What is the next step? Look, the process helps us all the way. It tells us what to do. The next step is to enter and do the tests of the key flows. Now, how do we enter? Using this 'Connect' button. Before we go deeper into the button, know that each instance also has here its...
36:20 Upgrade tab, which shows the upgrade status: 'Ready to test'. But careful, 'ready to test' means test as a technician. You, who are running this upgrade process, must test, because 'ready' only means the basics. All it tells us is that it started, and one or two more checks. So you still have to run the tests. It also gives us a date on which it will automatically be decommissioned. So the tests you do have to be done by that date at the latest, knowing...
36:56 That. We use the 'Connect' button to connect to the test instance. The test instance is this one here; we could go to that link, but of course we do not know the password to log in. If I go to the link, it loads the test website, but I do not have the username and password to log in. So in your case you use the Connect button, which runs a quick check that no errors appear, that the screens and modules load well, you enter a module and make sure there are no problems, you open the views...
37:31 Sales, invoicing. In other words, before this even reaches the support team, before it gets to the support team, you have to make sure everything loads well: at least the main menus, and that there are no obvious errors. But since in an Odoo database there is so much to test, this is where you can get help doing the tests with an artificial intelligence agent, and for that you have the Glux space from Ganemo.
38:04 Glux is Ganemo's product where we create agentic spaces, where AI agents assist you on various topics. There is a space where you can do your tests. You tell your agent: test this instance and check that the whole upgrade has been successful, and it tests it and reviews it. So you even get help with that. But this is the best case, right? That we ran the upgrade and it went right. It came out green, and we can test it.
38:37 But you could also get an error. What technical tools do you have to fix errors? Any error you detect or identify as a technician, you have to use Hangar, which is also a Ganemo product, that gives you an integrated space connected to the instance you are reviewing, with access to everything you need to solve the problems. Everything is in Hangar. I need access to the code repositories, the project for this test instance we are...
39:12 Creating. Whatever you can imagine you might need at a technical level, the space has access to it. You do the work there, the improvements you want or need. And when you finish fixing the problem, you click 'rebuild image': rebuilding makes a copy that takes the corrected code and deploys it, without having to repeat the whole upgrade process. This is key. It does not get redone or have to be waited on, like we waited a moment ago...
39:42 For the entire upgrade cycle to run. No. Here it is simply rebuilt with the new image. And this cycle of fixing an error through my space in Hangar, then rebuilding, then fixing again and rebuilding again, is a virtuous cycle that will repeat as many times as needed. Whatever it takes to resolve the incidents, you repeat that process. And once you have completed the process, or after each rebuild, you repeat the test.
40:17 You connect, you use the agentic space in Glux to do the necessary tests, but you test. And if you are thinking, 'Fernando, but connecting and opening a user interface to see Odoo like a regular user, that is not a technical matter'. Well, in that case, if that is how you think, you should not work at Ganemo, because here our technical team knows the product and knows it at the user level, at the functional level, not only at the code level.
40:48 And if after testing you consider the process good, the instance good, and the Odoo running there good, what you do is something as simple as moving your task from doing to Testing. And as I told you, moving it to testing is passing the ball to the other side. You have handed over the baton. From there, it is up to the customer. Yes, to the customer.
41:18 That is why it is very important, and why we insist that you, as the technical team, must do all those corresponding tests. You have to make sure everything is right. And the fact that you change this to testing also automatically updates the main task. Let's see, because two very important things have happened: you have moved it to testing, but what happened to the main task? Two things. From here I could enter the main task, but since in the end this is...
41:50 The flow the other profile sees, the upgrade functional profile. I put on the upgrade manager's hat and enter the task, my project, to see the task. Look, the task is already in phase 2. Now you understand what phase 2 means, and you see that the tasks move automatically in their pipeline. I enter phase 2. What happened when the developer moved their task to testing? Number one: my task changed stage. Number two: the customer is now being told what they have to do.
42:23 Look, as the customer: an email just went out to the customer and the task followers, saying 'your Odoo 19 test database is ready'. Incredible, a complete email, they even give you the URL to enter and do your tests. Remember: the production database at this point is not touched. Your users keep working as always. This is a copy of your production database that is already on the new version. And what for?
42:56 So you can test, so you can get trained, so you can identify what changed and where you have doubts. And not only you as a user; sometimes you are the administrator on the customer side, not in your company, no. Your users have to log in. Pass this link to all your users, forward this email, share it within your company, and have each user log in and do their day-to-day, not just register their invoice, look at that report, reconcile that...
43:27 Bank, review the website, set up a campaign, send a quote. What for? So they test for real, so doubts come out, so observations come out, and you give us those observations afterwards. You can even use an artificial intelligence agent for your review, as we have already explained. So subscribe to the channel and do not miss any of our videos, because we have already explained how you connect an AI assistant to Odoo, very easily.
43:58 And if you have a checklist of your processes and your upgrades well documented, it is as easy as telling people: this is my manual of the processes I run in Odoo, verify that everything is working well on this new version, and get help from an agent for your review. I am giving you ideas, but however you do the review, it is your responsibility as a customer to make sure everything works well, and you have a deadline: you have to do the tests before that deadline, and...
44:30 If something is not right, you simply let our upgrade team know; the same email tells you how to notify the team. It gets fixed, a new version of the copy is prepared for you, and you test it again. Preparing a new version means you get another email telling you that you can test and that it has been fixed. How would we summarize the complete cycle you as a customer have to follow? That is: you observe, and in our case, based on that observation, the engineering task...
45:02 Not this, which is the main task: the engineering task goes back to doing. You leave it. Let's go into the engineering task. Remember I am acting as the functional manager now, so this engineering task would have to go back to doing. If necessary, subtasks are created to solve the identified problems, and the upgrade technical team takes the tasks that are in doing and advances them with priority. And this whole cycle can also last as many times as needed...
45:35 Necessary. And while this cycle lasts, the functional manager's main task stays in phase 2. Unlike engineering, where its engineering task can indeed go from testing to doing, from testing to doing. And when you finish your tests as the customer, you simply reply here, you send a message that we will see here as a reply, where you tell us: tests done satisfactorily, we are ready, go ahead with the upgrade. You give us the approval...
46:07 Your team is trained, everything was tested, and that is why you write back and tell us: done, proceed with the upgrade. What do we do at that point? At that point, the engineering task stops being in testing and moves to done. Done means completed, carried out. Who changes that status on the engineering task? The upgrade functional team does not, but it is done because there is the customer's approval. So from the engineering team you forget about it, that is why I said...
46:42 Once the engineering team leaves its tasks in testing, the ball is in another court, in another game. They focus on what is in their backlog and in their doing, because what is in testing, if it no longer has to be in testing because all the tests passed, the support team moves to done. And if there is any observation, they send it back to doing. And note that now that it has moved to done, the stage here at the top has also changed, and it tells us...
47:13 This is no longer in phase 2. Phase 2 was the customer tests. Now that the customer has given us their confirmation, it moves to the cutover stage. And what do we call cutover? Cutover means scheduling a date on which the old Odoo version is no longer used, the production version you are using right now, and from then on the new Odoo version begins to be used. That is why the banner here tells you 'preparing the final instance for cutover'.
47:46 A few minutes. Then you press 'schedule cutover'. Wait a second. I will refresh to see whether the instance to schedule the cutover has been created. Now yes. The banner no longer appears, and the new 'schedule cutover' button appears. From your same task, as functional upgrade manager, you schedule the cutover. The cutover wizard opens with the schedule option active. If you choose the other option, run now, it does exactly the same thing, only it is scheduled...
48:20 In 5 minutes from when you confirm. Also, for safety, it asks you to confirm that the customer has already been communicated and notified. Because if I have not told them anything within 5 minutes, they may not get the message. The wizard will send an automatic message, but 5 minutes does not give them a chance to read it, so you have to confirm they have been notified now. The most usual thing is that we use the first option, schedule. We choose a date before running it. Let's set it...
48:52 For the same day today, we choose the time we want it to run, for example 6:15, and the stability days: how many days the previous version will be available, that is, the current one before cutover, before it is completely deleted. It is like a safety cushion where its version is kept, prior to the upgrade. And at the bottom you have very important data about how long it is going to last...
49:22 This process, or if there were some problem, for example, another banner appears. I am doing it on purpose, I will set it to one o'clock. You see, if you chose a time at which you cannot do it, a new banner warns you and helps you. It says: between such hours certain processes run, so it is better you do not use those hours. Since we were setting it to 6:30, there is no problem; the banner disappears. After choosing that hour, or a valid time, in the maximum downtime section it warns you.
49:56 For example, the migration of the copy, which is the one we have been working on with you, took 7 minutes, with margin. There is a migration budget of 40 minutes, and an expected maximum downtime in this case of 2 hours and 27 minutes. This is important because the customer has to know how long they will be without the system, without a doubt, even when the upgrade is done at night, at a time when theoretically nobody is using it. Even so...
50:26 It is important that they know, and also there are upgrades on giant instances that last many hours, and not even the whole night and the whole early morning is always enough to do the upgrade. So all the more reason, if it is going to interrupt their working hours, it is good for them to know how long they will be down, or rather without a system to continue. We have to accept this maximum downtime. If we do not accept it, it means you have to work on reducing these numbers.
50:57 In a way, the usual thing is simply to accept it, because it is a number based on reality. We do not make this number up. It is what the migration of its own test copy actually took, plus a few minutes of margin. If you are a customer, when you receive an email, which I will show you in a moment, with the date and the number of minutes your app will take, what you have to do is...
51:28 Organize your team during that window, when Odoo cannot be used. That is why it is ideal to schedule it outside your operating hours. We continue, and some tasks that must be done before scheduling appear. First it says 'test webhooks'. We click 'test webhooks' here below, the test runs, and it tells us it responded fine. Then 'test watchdog'. Let's click 'test watchdog' here, and finally we...
51:58 Get the result, and it tells us 200. What does that mean? That everything is correct. 200, 200. In other words, before scheduling, the system forces me to do these two life tests. The watchdog is an independent process. If at midnight or in the middle of the early morning the cutover gets stuck or the system itself goes down, someone finds out. The message arrives at our infrastructure channel, because the watchdog can use multiple...
52:32 Channels, thanks to the webhooks that are tested and working. A cutover that fails silently is the worst thing that can happen, and we do not leave that to chance. And now we are going to press schedule, but first you will be wondering about this 'check safeguards' button. Now it is not necessary to click it; in fact, do not click it, because it will take you longer in a regular process. Simply schedule, and when you schedule, Odoo takes care of checking all the safeguards...
53:07 Yes, this is only if you want to check the safeguards without scheduling, and it is unnecessary: we schedule directly. You see this message appears, indicating it is already scheduled, and in the banner it tells you it is checking the safeguards before scheduling the cutover. With the schedule button, as I said, it is mandatory: it checks the safeguards at that moment, and that can take a few minutes. As it tells you, the important thing is that as you go along it keeps you informed...
53:38 So you do not feel lost not knowing what to do or what happened here. Do not feel abandoned: it guides you. Let's wait a few minutes, and then we click refresh to continue. Note that while it is checking the safeguards and has not finished scheduling, we have no deadline assigned yet. Let's click refresh. And see, the schedule cutover button is not there either, because it is already scheduled; there is an assigned deadline, which is the one that was registered with you in the scheduling wizard...
54:11 Scheduling. Also, if we visit the message chat, you see the email already sent to the customer with the scheduled date details, the support channels, and, importantly, what I mentioned: the expected maximum downtime, so they can organize their team. That is why those minutes of safeguard waiting are important, because Odoo checks before committing to a date with the customer, because it has already...
54:41 Sent an email to the customer, and it makes sure the scheduled cutover can go ahead without problems. All safeguards say continue. And what if you need to change this date? That could happen, because here you cannot edit it, for security reasons, since you have already sent an email to the customer promising them a date. So in any case, how do you change it? First you have to notify the customer. And here, in the upgrade tab of the same main task, you will see that the final instance has already been created, that is...
55:15 Once the cutover or upgrade finishes, this is your new instance. Good, you can enter that instance. I will enter it to show you. And we go to the upgrade section and to the cutover part. And you see here it says 'cancel scheduling'. If you click it, it asks for a reason and the scheduling is cancelled. Then you can go back to the main task, and from here the schedule cutover button will appear again so you can start the whole process again, which involves a new scheduling that...
55:49 A new email will be sent to the customer too, about when it is scheduled. If you do not want to go as far as the final instance, look, we have also made the cancel scheduling button available here. But I will go a bit deeper into which safeguard checks Odoo has run. Before cutting over, at the moment I am scheduling, the system checks nine things. If one of the first eight is missing, the cutover does not start and nothing is touched.
56:20 The ninth only warns. First: there is an approved copy. You have it with you, we generated an upgrade copy, it was tested and marked as approved. But let's see: if we enter from the main task, we can go to the upgrade tab, the upgrade test database, I enter, and from its upgrade tab we have to remove the tested mark. What does that mean? That it has a mark saying it has been tested. And you will say, at what moment was this test instance marked as...
56:52 Tested? Remember that in the flow, during the process we have been working through with you, this engineering task moved to the done state. In fact, at what point did it reach that state? When all the phase 2 tests passed and we have communication with the customer that they passed the tests. At that point, this moves to the done stage. And automatically the test instance is marked as approved.
57:22 Well, you do not even have to mark it manually. The second check is whether the cutover is within its time window and outside any nightly maintenance, and does not overlap with other jobs being run. Third, whether the engineering task is closed: the customer approved. Fourth, whether there is a recent and verified backup of the production database. Fifth, whether the attachments are copied and verified. Sixth, whether there is no other cutover in progress on the whole platform.
57:56 If the customer uses the SQL connector, it checks whether its connection is ready to move to the new version. Eight: the image. An automatic check confirms that the final instance was built with the same code as the approved copy. And finally, the ninth, which is only a warning, does not block anything, but an automatic check confirms that no module was installed in production after the copy without code for version 19 or an implemented migration recipe.
58:32 All these reviews, all these points, used to be decided by a person with an approval; today the code decides, and there is no way to skip any of them. For example, imagine you passed the upgrade copy I showed you as approved, but you rebuild it because you made some fix using Hangar, you changed something. Then that approved mark stops being valid: it is unmarked automatically, and on purpose you have to mark it again, otherwise...
59:05 It will not let you schedule the cutover; it is a security measure. Now, if you are a partner, copy this list I just gave you, even if you do not have a system that checks it for you: turn it into a mandatory checklist before every cutover. Now that it is scheduled, let's go into the final instance. It has already been created but no upgrade has run yet, because it is scheduled for a future date. It will run in about 20 minutes, approximately, but a banner appears indicating there is a scheduled cutover. It warns you...
59:40 That it runs on its own, so do not press manual buttons. Now yes, the upgrade has started, and the scheduled cutover is in progress; it is executing. From here on, the system operates by itself. And during this cutover, it is important: the customer is out of service. Your customer will not be able to log in to Odoo during this cutover process. Remember you were notified in advance by email.
1:00:10 Also, it warns us that we can follow the progress in cutover attempts here at the top, in the smart button: cutover attempts will show every cutover attempt you have had. At this moment we are on this one here, the first one, and all the information related to your cutover is there. And look how nicely it tells you, it narrates all the steps it is running, and here you see from when we scheduled the cutover and what started afterwards.
1:00:41 The scheduled cutover begins, sets up a watchdog, the watchdog step is done, shuts down the old production database for safety so the customer does not use it, the migration is launched, and so it progresses by itself, in this event thread log, which serves as an audit trail because it is immutable. Let's see the full detail of what is running automatically while we wait for it to finish. We are going to do a couple of things, reviews first: the main upgrade task is still in the cutover stage...
1:01:15 But it already has its execution date. In all this process I am showing, since I scheduled it as the support lead of 'abril', I no longer have to do anything else. From then on, everything works automatically; it operates by itself in my task pipeline manager. I am going to see all the tasks here, and those that have a planned date, either start today or already...
1:01:47 Have a future planned date, I ignore those; I do not have to worry about them. I do not have to be thinking, oh, I have to remember this task is pending. No, the system takes care of it. Which ones do I take care of? The cutover tasks that do not yet have their planned date, their deadline assigned, because that is how I have to schedule: making sure to set the scheduling date, everything I just showed you about how a cutover gets scheduled. And from then on I do not sit waiting...
1:02:21 For the upgrade to start on my instance. That would be impossible, a madness, because I did not schedule it for half an hour from now. I scheduled it for some days in the future, for next week. So I am not going to wait for that date to arrive. What do I have to do? Nothing. Scheduled task, planned task, next, next, next. This is upgrade manufacturing, and we have to schedule and launch all the upgrades...
1:02:52 Physically possible for each upgrade technical team: we should be launching 20 upgrades every week, so every week we are talking about 80 upgrades a month. That is the ideal, because sometimes the upgrade technical team is not dedicated only to upgrades; we leave them the odd task, and so it is understood that sometimes they do not meet those goals. But if not, they have to meet those numbers. In our case, the upgrade is still going to...
1:03:27 Be running in a few minutes. I will be back with you in seconds, and I am back, ladies and gentlemen. The upgrade has just finished. We see the task is no longer in cutover. It automatically moved to the upgrade closing stage. We go in to see what happened. From your upgrade tab we go into the final upgrade instance. Wow, beautiful, ladies and gentlemen, now we have full control over all the buttons...
1:03:58 Complete, because this is a production instance now. But let's see what happened in the meantime: in cutover attempts, the attempt we just ran is green, and there is the complete event log. Look at the number of tasks and activities it has completed on its own, until it finally reaches the end, where it finishes with its last activity. If something had failed at some point, the system rolls back on its own and leaves the database...
1:04:32 Of the previous production data, the version the customer was on, running. The next day, when the customer's users try to log in, they will get in without a problem and keep working as if nothing had happened, but they will be on their version at that moment. In this case, since the cutover was successful, what will happen is that when the customer logs in at the same URL, on the same system, as they log in every day, they will start working as if nothing had happened...
1:05:06 But they will already be on the new version of Odoo. If we enter, for example, the main task, we saw it already automatically moved to upgrade closing. And an automatic email was also sent to the customer telling them that their Odoo instance is ready, including the link to enter, but the link does not change. So they will go in and work as if nothing happened, and they will not even...
1:05:38 Find out that the anchoring obviously happened; of course they know, because they were notified, but their users are not affected in the slightest. This message has important parts. What do we recommend doing today? If something fails, where do you have to get in touch? What are the channels? It is always important, communication is key in everything. If you need support after the upgrade, you have access to an exclusive promotional pack if you contract it after the upgrade. Why? Because we want to help you incorporate the new version well, to give you guidance and support, so...
1:06:12 If you already have valid hours in your support pack, congratulations. If you do not have them, you can contract it. It is obviously not mandatory, because you can self-serve and self-learn; all the knowledge is public and you have access to all the manuals we provide. So you could supply yourself with what you need without help. But if you need to go faster, or for us to help your users, you take advantage and contract a promotional pack. The post-upgrade stage we consider the seven days after. After that there is no more access to promotional packs and resources.
1:06:46 So you can learn about the new version you are entering. Now, let's go to the moment of truth: I am going to open this link to see what is there. We enter from the same URL as always to the customer's database, with the difference that this is version 19, so their users log in with the same username and password, with the same two-factor authentication. Everything, everything stays the same.
1:07:17 Also, if you enter through your portal, we will see Ganemo's portal, which is very important. All our customers have to have access to their portal, because from there they basically manage their database. So you go to the instances section and there you see it. You have your card already updated. This is the v19 one. You only ever see your current card. So from here you could connect, or connect as you always have, but...
1:07:47 It would go directly to the new version. And if you manage the instance, you can see you have a history; in this case it says the deployment was successful. But for everything else it is the same as you already knew: your same URL as always to log in. And look, it is important: there is a URL for your previous version. That is the 28-day backup we said we would keep as a safety net.
1:08:17 It has its own URL, and in an emergency, if needed, it can be accessed there. By default, this is inactive. If you need to activate it, you contact the support channel. The idea is that this never has to be used. Needing it is for a critical emergency. Most commonly the customer does not even find out about this new URL or need to know about it, because they keep working with their regular URL, but if you as a customer have...
1:08:48 Access to the portal, well, you should have it, so you know everything is kept there as a safety net. And also at the level of connectors, or the SQL connector you have on your instance, everything keeps working exactly as before. If you had your Power BI, your Excel, your reports, your external tools connected to Odoo or connected directly to your PostgreSQL, that keeps working identically. You do not have to change any configuration.
1:09:19 Your reports will keep updating without a problem. Also, in the meantime, this new production database, on the new version, already starts generating its backups automatically at the corresponding time. And since everything started with a task, remember? How nice the story is. If we go back a few minutes, to the planning, remember what it did? It created this task. And everything stays associated with this same task.
1:09:50 And during those 28 days we gave for the previous database to still be kept at a URL, which the customer can also see from their portal. While that happens, while those 28 days we allowed for testing have not finished, which could be fewer at our total discretion, in the meantime this task stays in the upgrade closing stage. If we go back to tasks, the upgrade closing stage is a stage that is folded by...
1:10:22 Yes, because from there we forget about it. That is, everything flows normally, unless the customer reports something, and in that case we would have to access it and review what happened. But otherwise, it stays folded, because once that grace period of 28 days, or whatever has been configured, ends, this task will automatically move to its final stage, which is the done stage. There that task will live forever as something completed, but in the history, if at any...
1:10:55 Moment we want to go in and review and audit whatever is needed, it will be there. Let's review what you have just seen: planning with clear tasks; a test copy with real data that does not touch the customer's production database; the customer testing their day-to-day operation and approving in writing a scheduled cutover with a known maximum downtime; nine safeguards that cannot be skipped; a watchdog in case something fails silently; the customer's connections intact; and 28 days of backup before final closing.
1:11:31 An upgrade stops being scary when every step has an owner, a test and a rule. If you are a customer, you know your role. If you are a partner or consultant, take the process, replicate it, and rescue what is useful to you. And if you want us to do your next upgrade with you, you have our link in the description. Subscribe to the channel to keep learning, and if you are a creator of value, see you there.